patching...
Update: Want to get your Hatboro and Horsham news in your inbox every morning? Sign up for our free newsletter! »
Welcome back, Patch Blogger!

Construction

Monday, May 20, 2013

YMCA Demolition, Construction Underway

Gina TB

3:37 pm on Wednesday, May 22, 2013

How does a YMCA that has a swim team NOT have and outdoor pool????? who wants to swim INSIDE during the summer?????   more ›

Sunday, January 27, 2013

Water Main Work Creates Traffic Woes on County Line

Traffic restrictions at County Line and York roads has caused a build up of traffic congestion at the busy intersection. The section is expected to be complete by next week.

Traveling along the County Line and York road intersection has its harrowing moments, but the past two weeks have been practically impossible for motorists. The ongoing project to replace seven miles of water main pipes made a stop at the intersection last week, forcing the stretch of road down to two lanes while crews prevented drivers from making left turns during late morning hours into the early afternoon. For example, if you are traveling westbound on County Line, and wanted to turn left on York, workers will stop you and direct you to keep driving on County Line. Though the project is still months away from completion, Bucks County Water & Sewer Authority spokesman Patrick Cleary says that section will be cleared of construction by …

Maureen Malachowski

8:52 pm on Wednesday, January 30, 2013

love how the dump trucks from Bucks country water & sewer are using Sherwood Rd as a turn around- why should they be using our Horsham Township streets with those big trucks ? County Line is a disgrace, the paving company that is doing the repair work should be ashamed of their work--- I believe it will cause many accidents due to the ruts and pot holes . I wonder if the state will fix the mess?   more ›

Monday, October 15, 2012

Hatboro Officials Mum on Firehouse Project

Citing the 'issue of litigation,' Hatboro Council President John Zygmont declined to say when the long-overdue construction at Enterprise Fire Company would conclude.

By all accounts, the volunteers of Enterprise Fire Company have a nearly completed 2,500-square-foot addition on the back of the firehouse that they cannot use. The contractor for the roughly $887,000 project, Mark Gill of Titanium Inc., since August has had two pages of punch list of items in need of reconciling. Gill told Patch in July that there was less than two days of work left. Yet, three months later, the building addition sits, unusable and unoccupied. And, Hatboro officials have declined to say when the addition will be complete, what steps are being taken to urge Gill to finish the work, or if the more than year-long delays have compromised a state grant reimbursement of $500,000. Borough Manager Fred Zollers, who is also a …

Thursday, August 30, 2012

Byberry Road Construction Slows Traffic

Road work is being carried out near the SEPTA train station on Byberry Road in Hatboro.

Monday, August 8, 2011

Hatboro's Fire Station Expansion Set for Fall Completion

Additional costs and other unexpected issues like flooding, are not expected to cause major delays in the completion of Enterprise Fire Company's 2,500-square-foot addition.

Despite a few setbacks, the Enterprise Fire Company expansion project is on pace to be completed by mid-October, officials said.  Recent heavy rains caused flooding of the fire station’s basement and engine bay area, Fire Chief Keith Gordon said. The fire department’s generator was damaged and records were ruined, he said.  “There is a sump pump down there, but there was so much water the sump pump couldn’t keep up with it,” Gordon said of the two to three feet of water that entered the basement. “You’re going to have a little bit of that problem with any construction issue.” Hatboro Borough Manager Steve Plaugher said the fire department’s insurance company would cover the expenses related to flooding. Late last month, work had been …

MJG

6:37 pm on Monday, August 8, 2011

If they didgood luck geting the truth. Someone from the boro was encharge of this and screwed up. They should get a clue!!   more ›

Tuesday, August 2, 2011

Hatboro Seeks Third Party Review of Police Building, Operations

The no-cost assessment would be carried out by the Pennsylvania Governor's Center for Local Government Services.

As Hatboro Borough Council considers spending an estimated $2.2 million to demolish the outdated police building and construct anew, officials are seeking a third party assessment of plans related to police operations. The council, during last week’s meeting, unanimously approved a resolution to request that the state’s Governor’s Center for Local Government Services conduct a police department assessment. The effort, recommended by Hatboro Police Chief James Gardner, was last carried out in the 1980s, he said. Suggested improvements from that study led to building renovations. “It’s not bad every once in a while to have a third party come in and take a look at things,” Gardner said. Before the council commits to spending more than $2 …

Comment_arrow

Dolores Forget

1:20 pm on Tuesday, August 16, 2011

Moving the police station to the Wachovia building seems to be a good idea -- I wonder if it has been considered. They'll even have a "vault" for detainees.....   more ›

Got a Hot Tip?
 
 

Videos